Mon May 27, 2019 12:00:28
فارسی | العربية | English

Damavand Petrochemicals Power Plant Phase 1 opens in Dr Rouhani’s presence

Phase 1 of Damavand Petrochemical Company Power Plant, with production capacity of 650MW of electricity a year was opened in Dr Hassan Rouhani’s presence.

news id: 105913 -

Tue 04 - September 2018 - 11:15

In the ceremony that was held on Tuesday in Assalouyeh in Dr Rouhani’s presence, in addition to opening Phase 1 of Damavand Petrochemical Company Power Plant and additional services of Phase 2 of Assalouyeh, Dr Rouhani visited different parts of the project and we briefed by the project managers and experts on the processes.

Phase 1 of Damavand Petrochemical Company Power Plant consists of 14 turbines and steam generators that is capable of producing 650MW of electricity a year.